Subcontractors are missing deadlines on your construction site. How can you ensure timely project completion?

Subcontractors missing deadlines can derail your entire construction schedule. Keep your projects on time with these strategies:

- Establish clear terms. Define deadlines, penalties for delays, and incentives for early completion in contracts.

- Regular progress check-ins. Schedule weekly meetings to monitor progress and address issues promptly.

- Foster strong relationships. Build rapport to encourage subcontractors to meet their commitments.

How do you handle missed deadlines in construction? Feel free to share your strategies.

Construction Management Construction Management

Construction Management

+ Follow
Last updated on Nov 20, 2024
  1. All
  2. Construction
  3. Construction Management

Subcontractors are missing deadlines on your construction site. How can you ensure timely project completion?

Subcontractors missing deadlines can derail your entire construction schedule. Keep your projects on time with these strategies:

- Establish clear terms. Define deadlines, penalties for delays, and incentives for early completion in contracts.

- Regular progress check-ins. Schedule weekly meetings to monitor progress and address issues promptly.

- Foster strong relationships. Build rapport to encourage subcontractors to meet their commitments.

How do you handle missed deadlines in construction? Feel free to share your strategies.

Add your perspective
Help others by sharing more (125 characters min.)
23 answers
  • Contributor profile photo
    Contributor profile photo
    Tamirlan Bakirov

    Construction QA/QC Chief | Quality Management, Quality Assurance

    • Report contribution

    To address subcontractor delays, start by identifying the root causes, such as resource shortages or unclear expectations. Hold regular progress meetings to enhance communication and ensure alignment on deadlines. Revisit project schedules to reallocate resources, overlap tasks, or prioritize critical path activities. Review contracts to enforce penalties for delays or offer performance incentives. Provide support if subcontractors lack manpower or materials. Monitor progress closely through daily site inspections and maintain a problem-solving approach. If delays persist, consider replacing underperforming subcontractors to avoid jeopardizing the overall project timeline.

    Like
    8
  • Contributor profile photo
    Contributor profile photo
    Dean Calcutt MCIOB CMgr MCMI

    Decarbonisation & Domestic Retrofit

    • Report contribution

    To ensure timely project completion, focus on the critical path by identifying and prioritising tasks that impact the overall timeline. Strengthen communication through daily updates and a clear point of contact, and set milestones with regular progress tracking. Address bottlenecks such as supply delays or access issues, and provide support if subcontractors require resources or training. Enforce penalties for missed deadlines while offering incentives for timely delivery to maintain accountability and motivation.

    Like
    4
  • Contributor profile photo
    Contributor profile photo
    Peter Gaed

    Project Manager | Civil Engineer | Expert in Delivering Successful Construction Projects | Committed to Excellence in Project Planning and Execution | Driving Innovation in Civil Engineering.

    • Report contribution

    Strengthen communication, set clear expectations, and monitor progress regularly. Address delays through collaborative problem-solving, reallocate resources if needed, and implement penalties or incentives to ensure accountability and maintain timelines.

    Like
    3
  • Contributor profile photo
    Contributor profile photo
    Mrutyunjay Suresh Chandra Giri

    Electrical Engineer-B.E(Honours )| Transmission and Distribution Systems Expert | Global Operations | Mentorship | Psycho-Techno-Commercial Expert | Liberal Arts Expert | Business Analyst | Organisation Set-up Expert.

    • Report contribution

    My proven prospectives as stated below: 1) Always evaluate subcontractors proficiency and efficiency as per the construction needs, prior to deployment. 2) During on going construction phase periodically quantity, identify, verify and measure as per schedule. Any deviation desire output, take corrective action immediately. 3) Always maintain proper scheduling, sequencing, integration and mapping as per construction scope. 4) If required, provide mentoring as per construction needs. Sure this should prevent from construction delays.

    Like
    3
  • Contributor profile photo
    Contributor profile photo
    Dhinakaran Purushothaman MBA MRICS MIS

    Mentoring & Career Guidance | Construction Expertise | Chartered QS & Civil Engineer

    • Report contribution

    In addition to the provided strategies, we should also ✅ Prepare for contingencies with backup plans to maintain a list of alternative subcontractors for critical tasks. And reallocate resources by adjusting schedules or deploying additional resources when delays occur. ✅ Analyze and adjust by conducting a Root Cause Analysis to investigate the reasons for missed deadlines and implement preventive measures. ✅ Lessons Learned: Use post-project reviews to improve performance in future projects. By blending accountability with support and fostering open communication, we can address delays effectively while maintaining productive subcontractor relationships. 🎯🗓️🏗️

    Like
    2
  • Contributor profile photo
    Contributor profile photo
    Shaik Faiazuddin

    Contracts Management Expert, PMO Consultant,LL.M (Oil, Gas and Renewable Energy Law) MRICS PMP PEng (Civil), delivered Giga projects Infra, Real estate, PPP, strategy, project, cost management, Training and Development

    • Report contribution

    I ensure to work closely with subcontractors and identify the reasons for the delay and endeavor to support them in achieving the common goal which is delivering the project on time and within budget. Sub contractors delays usually happens due to scarcity of funds, resources, poor planning, lack of direction, less management back up. I identify the proper reason and make them working

    Like
    2
  • Contributor profile photo
    Contributor profile photo
    Farid Tafazzoli, PMP®, MBA

    Construction Project Manager | Proficient in Stakeholder Engagement, Team Leadership, and Cost Control

    • Report contribution

    Missed deadlines can disrupt the critical path, but proactive management keeps projects on track. Start by clearly defining milestones and using real-time tracking tools for visibility. Foster accountability with collaborative progress reviews, addressing delays as opportunities to streamline processes. Incentivize excellence with performance-based bonuses while enforcing penalties for non-compliance. If delays persist, engage backup subcontractors from a pre-vetted pool to avoid bottlenecks. Strong communication and a culture of problem-solving ensure deadlines aren't just met—they're optimized.

    Like
    2
  • Contributor profile photo
    Contributor profile photo
    Brigman Rees

    Project Manager • Logistics Engineer • World's Best Dad (Certified)

    • Report contribution

    Consistently missing deadlines is not a matter of knowing, it's a matter of doing. Why aren't your subcontractors holding to their word and meeting your deadlines? Whether you're a business owner, operations manager, or project manager, assuming everything's squared away internally, you need to assess where this relationship is breaking down. Everything is built on respect in the construction industry and it's your job to establish a culture of mutual respect. Request they come to your office, then address your performance concerns and hear what they have to say. How will they rectify the current dynamic? Do you need to put temporary penalties for missed deadlines? Fairly, firmly, and respectfully put the ball in their court.

    Like
    2
  • Contributor profile photo
    Contributor profile photo
    Terry Tracy

    Assistant Vice President at Trilogy Health Services, LLC

    • Report contribution

    Use your job site tools to monitor schedule progress. At your contractor meetings, go through your schedule, at least 2-4 weeks out. Identify contractor weekly goals, done at your previous meetings, to ascertain their progress. Perhaps try “reverse scheduling” process initially, where the contractor base is asked to participate in their critical path completion. Done with different color post it notes on a job trailer whiteboard, the individual contractors lay out their progress, allocating manpower/ materials themselves. They will see predecessors in front of them, as well as those that will follow. The fellow contractors will be able to see the completion as forecast, or determine where the miss occurred. This is invaluable for the job.

    Like
    1
View more answers
Construction Management Construction Management

Construction Management

+ Follow

Rate this article

We created this article with the help of AI. What do you think of it?
It’s great It’s not so great

Thanks for your feedback

Your feedback is private. Like or react to bring the conversation to your network.

Tell us more

Report this article

More articles on Construction Management

No more previous content
  • You're overseeing remote construction teams. How can you guarantee effective task delegation communication?

    33 contributions

  • Your construction project faces scope changes. How can you ensure your team stays aligned and productive?

    51 contributions

  • Your construction project timeline is tight. How do you handle sudden client demands for tech-driven changes?

    18 contributions

  • Your construction team is racing against the clock. How do you ensure quality isn't compromised?

    29 contributions

  • How do you navigate conflicts with suppliers who deliver subpar materials impacting project timelines?

No more next content
See all

More relevant reading

  • Construction Management
    You're facing clashes between subcontractors and client demands. How will you find common ground?
  • Construction Management
    What do you do if subcontractors and suppliers fail to meet your logical reasoning standards?
  • Construction
    How can you resolve construction cost conflicts with clients and contractors?
  • Construction Management
    Team members are clashing over material quality. How will you ensure they reach a resolution?

Explore Other Skills

  • Building Design

Are you sure you want to delete your contribution?

Are you sure you want to delete your reply?

  • LinkedIn © 2025
  • About
  • Accessibility
  • User Agreement
  • Privacy Policy
  • Cookie Policy
  • Copyright Policy
  • Brand Policy
  • Guest Controls
  • Community Guidelines
Like
6
23 Contributions